Please see attached plans and explanation beneath regarding remaining works at Mornington Pier Forecourt.
Unfortunately Parks Victoria have not been able to complete the power relocation works, so the project will not be completely finished before Christmas. This delay was a concern from the outset, hence the staging plan which was sent to you all on the 16th September.
The staging plan means that the forecourt/ carpark area will be left clean, safe and usable for the Christmas and January period, with no construction works planned. The Contractor will then return in February or when Parks Victoria has relocated the electrical services and complete the remaining tasks.
If you require any further information please let me know.
Kind regards,
James
Click on drawings
Work ot be completed prior to 24th Dec
Work to be completed in Feb
JAMES MCNEUR | Project Manager | MORNINGTON PENINSULA SHIRE